Excited to live at The Standard at West Lafayette? Check out this detailed construction timeline for updates on our progress, expected move-in dates, and more. Reach out to our leasing team for more information.

  • 2026
    October

    The building’s frame is complete! Crews are finishing the outside brickwork, starting the roof and lifting the rooftop pool into place. On the lower floors, apartments are getting cabinets, countertops and flooring.

  • 2026
    November

    The tower crane comes down. Exterior siding and storefront windows keep going up. The first floors of apartments are finished. Elevator installation begins.

  • 2026
    December

    The roof is done and the building is fully sealed from the weather, so crews can keep working inside all winter.

  • 2027
    January

    Permanent power is turned on. Drywall reaches the top floor, and more floors of apartments are finished.

  • 2027
    February

    Drywall is complete throughout the building. The lobby and amenity spaces come together, and furniture starts arriving.

  • 2027
    March

    All apartments are finished! Elevators, hallways, amenity spaces and landscaping are complete.

  • 2027
    April

    Signs go up, exterior siding, the parking garage is finished, and building systems are tested.

  • 2027
    May

    Final safety and city inspections. Apartment furniture begins moving in.

  • 2027
    June

    Furniture is in. TV, internet, Wi-Fi and security cameras are installed. The pool is opened.

  • 2027
    July

    Final touch-ups and quality checks. The leasing and management team moves in and gets ready to welcome you.

  • 2027
    August

    Move-In Day! Residents move into their brand-new apartments starting August 12th.